Terms Of Use Privacy Statement

Monitoring Agency checks delay of beach beautification

Latest News Kuwait City 10 Aug 22
Monitoring Agency checks delay of beach beautification
Monitoring Agency looks into delay of beach beautification project in Kuwait.
Fee
Event Location
Kuwait, Kuwait
Area
Kuwait City
Start Time
10 August 2022, 12:00 AM
End Time
31 August 2022, 12:00 AM
Website

The Government Performance Follow-up Agency has asked the Municipality to find out what difficulties and obstacles caused the delay in the tender of a beautification project, construction and maintenance works for public beaches in Kuwait, reports Al-Qabas daily.

The Deputy Head of the Agency, Mishaal Al-Baijan, said, in a letter to the municipality stated in Article 2 of its establishment decree No. 346 of 2007, regarding the follow-up of the executive position of government projects within each ministry or government agency in coordination with these bodies, and in light of the timetable approved for implementation.

As stated in Article 3 of the same decree that the Agency, the agency can exercise its powers, may contact the ministries and relevant authorities to obtain information, data and studies, and these authorities shall cooperate and coordinate with the Agency in this regard.

List of follow-up inquiries

■ Project implementation contract and the last monthly report for each of the contractor, consultant,
entity and project manager.
■ Certificates of material and temporal change orders, provided that the date of their issuance and
the reasons for its issuance are clarified from the beginning of the project to its date.
■ The approved completion percentage curves showing the planned monthly completion
percentages for the entire contract period and the actual to date.
■ Copy of the tables of the planned labor numbers for the entire period of the contract and the
numbers of actual labor to date.
■ Copy of the payment certificates that have been issued, from the beginning of the contract to its
date.
■ Table showing the value of the fines for the contractor’s payments that have been deducted from
the beginning of the contract to date, grouped according to the type of fine.
■ Table with dates of approval and disbursement of financial payments for the contractor, from the
beginning of the project to its date, showing the payment number and its value before
discounting. ■ Timeline of the project, including the difficulties and obstacles that caused the
delay in the project.

Kuwait beach beautification project